- Full Shop Tank fabrication (2 nos) include PWHT (Post Weld Heat Treatment)
- 3rd heavy lift project of shop fabricated tanks (9000cbm each)
- With diameter of 22.5m and standing at 28m high & Lifted with a 5,000MT SWL Sheerleg Floating Crane
Project Type: Process Plant
Symphony Project – E&I Works Package 1&2
Construction of double wall tank
Neste Singapore Expansion Project
- EPC of 22 no of tanks for Neste Singapore Plant Expansion
- Total capacity appx 180,000 cbm
Thai Oil – TOP New Tank Project
- Basic and detailed engineering for 5 nos. of atmospheric tanks
- Tank diameter is 30, 36, 39 and 60 meter respectively
- 2 nos. of 60 meter diameter with Aluminium Geodesic Dome Roof/Internal Floating Roof Full Face Contact (GRE : Glass Reinforced Epoxy Type)
- 2 nos. of 30 and 39 meter diameters with Fixed Cone Roof/Internal Floating Roof Full Face Contact (GRE : Glass Reinforced Epoxy Type) and other 36 meter diameter with Fixed Cone Roof
- Total capacity – 180,000 cbm
- Tanks (empty weight) – 3,450 Tons
- Atmospheric tanks products: Jet A1, Gasoil, MOGAS, TCP
- Safety man-hours w/o LTI – 420,000 mhrs
- Design and supply of materials, fabrication and erection of tanks, testing and inspection.
Upstream Project for Hygiene and Value Added (UHV)
7 nos. of 43,000 cbm spherical tanks & 20 nos. of 148,000 cbm atmospheric tanks
Arkema Lychee Project
The electrical installation work scopes for this project comprises supply of non-free-issue materials, installation, testing & commissioning of electrical equipment and systems in the substations. The work scopes in process & offsite utility areas are as follows.
- Motor control stations
- Power junction boxes
- Welding & power socket outlets
- Convenience outlets
- Power & control cables
- Termination kits, cable glands, termination sockets and all accessories to complete cable installation
- Cable ladders, trays, support for cable ladders and trays below 300 mm & accessories
- Complete outdoor lighting system including but not limited to light fittings, street lighting, fence lighting, plant area lighting, lighting cables, JBs & accessories
- Aboveground earthing system
- Lightning protection System
- Heat tracing system
XSBR Project – Mechanical, Piping, Electrical & Instrumentation Works
Mechanical & Piping Works:
- To provide scaffolding for equipment and piping installation as necessary.
- Supply and installation of holding down/ anchor bolts, studs, washers and nuts where not provided but deemed necessary for installation of equipment piping and structures on concrete foundations/plinths.
- Shop/Field fabrication or modification, erection, testing and painting of new pipe works.
- Supply material, fabricate, galvanizing, and erection of pipe supports.
Electrical Works:
- Motor starter
- Motor Control Station (MCS)
- Power Supply for Pumps, Package Unit and Lighting & Power Distribution Board
- Cable Supply & Installation
- Cable Tray/Ladders Supply & Installation
- Cable Termination
- Grounding
- Testing and Commissioning
Instrumentation Works:
- Control Panel In DCS room
- Instrument Installation
- Junction Box Installation
- Cable Tray/Ladder Installation
- Cable Installation and Termination
- Instrument Earthing and Bonding
- Instrument Air Header and Tubing Installation
- Relocation of Existing Instruments
Inspection and Testing
SADARA – South Tank Farm Project
Site erection of 28 nos. of tanks (include 5 nos. of Stainless Steels tanks & 2 nos. of double wall tanks)
Saudi Elastomer Project (SEP)
Pre-fabrication & site erection of 13 nos. of tanks & 1 no of sphere tank.
SADARA – Isocyanates Tank Farm Project
Shop fabrication of 10 nos. of Stainless Steels tanks.