Oiltanking Singapore – Phase 7 Expansion
- EPC of petroleum storage facilities of 187,500 cbm
- Total of 9 carbon steel tanks
- Detailed engineering work for tankage, civil, equipment sizing, piping, electrical & instrumentation works
- Procurement of tank farm equipment such as steel plates, piping materials, electrical cables, instrument tubing, instrument gauges, pumps and motors etc
- Civil works include foundation, bund wall, pipe racks, sleepers, sewer system etc
- Equipment works include installation of ship loading pumps, gangways, marine loading arms, fire monitor tower, jetty jib & etc
- Erection of CS external floating roof tanks and CS fixed roof tanks with CS internal floating roofs