ENOC – Refinery Expansion – Tankage Facilities Project
JAFZA Dubai, UAE
Fujairah Oil Terminal
Fujairah, UAE
Fujairah Oil Terminal – IMW Project
Fujairah, UAE
Port of Fujairah – VLCC Jetty No. 1
Fujairah, UAE
SEOT Phase 7A – Polyols Storage & Handling Project
Dubai, UAE
Farabi Pipelines Project
Yanbu, Saudi Arabia
ENOC – Refinery Expansion – Tankage Facilities Project
- PROJECT DESCRIPTION
EPC of 12 tanks, with 450,000 cbm storage capacity. Scope includes associated civil works, piping connections (including tie-in to existing refinery), mechanical works, electrical and instrumentation works and fire-fighting facilities
SCOPE OF WORK:
Engineering Design, Procurement and Construction:
- Civil
- Tankage
- Piping & Structures
- Equipment Installation
- Electrical & Instrumentation
CLIENT: ENOC Processing Company (LLC) (EPCL)
LOCATION: JAFZA Dubai, UAE
OWNER: ENOC Processing Company (LLC) (EPCL)
DURATION: Mar 2017 - Jan 2019
Fujairah Oil Terminal
- PROJECT DESCRIPTION
- Total storage capacity of 1.15 million cbm
- Product storage tanks 34 nos., slop tanks 2 nos., utilities tanks 4 nos.
- Product jetty pipelines
- Common facilities & utilities, including E&I works
- Building works including administration building & substation
SCOPE OF WORK:
Engineering Design, Procurement & Construction:
1. Civil
2. Tankage
3. Piping & Structures
4. Equipment Installation
5. Electrical & InstrumentationCLIENT: Concord Energy Pte Ltd
LOCATION: Fujairah, UAE
OWNER: Fujairah Oil Terminal FZC
DURATION: Nov 2012 - Dec 2014
Fujairah Oil Terminal – IMW Project
- PROJECT DESCRIPTION
Engineering, Procurement and Construction of the additional works which involved civil, piping (appx. 3000 BD) & structures, mechanical, electrical & instrumentation works.
SCOPE OF WORK:
Engineering, Procurement and Construction of the additional works:
- Civil
- Piping & structures
- Equipment installation
- Electrical & instrumentation
CLIENT: Fujairah Oil Terminal FZC
LOCATION: Fujairah, UAE
OWNER: Fujairah Oil Terminal FZC
DURATION: Jan 2015 - Feb 2016
Port of Fujairah – VLCC Jetty No. 1
- PROJECT DESCRIPTION
- Marine and jetty topside works
- 2.6 km twin crude lines 40” size
- Firefighting and utility
- Piping works (approx. 65000 DB)
SCOPE OF WORK:
Engineering Design, Procurement & Construction:
- Civil
- Piping & Structures
- Equipment Installation
- Electrical & Instrumentation
CLIENT: Port of Fujairah
LOCATION: Fujairah, UAE
OWNER: Port of Fujairah
DURATION: Sep 2014 - Jul 2016
SEOT Phase 7A – Polyols Storage & Handling Project
- PROJECT DESCRIPTION
Project involves residual engineering, procurement & construction of 10 tanks of 26,000 cbm of chemical storage capacity, associated civil & piping works of approx. 35000 dB, 325 tons of steel structure, mechanical equipment erection, electrical & instrumentation works of approx. 70 kms of cables, distribution transformer, diesel generators, MV switchgear, MOV actuators etc
SCOPE OF WORK:
Engineering Design, Procurement and Construction:
- Civil
- Tankage
- Piping & Structures
- Equipment Installation
- Electrical & Instrumentation
CLIENT: Star Energy Resources Ltd
LOCATION: Dubai, UAE
OWNER: Star Energy Resources Ltd
DURATION: Sep 2016 - Sep 2017
Farabi Pipelines Project
- PROJECT DESCRIPTION
- Connecting pipelines from Farabi to ATTL, and ATTL to Berth 21
- Construction of new pump station (6 new pumps)
- Supply installation of 2 MLA
- Associated E&I and civil activities
SCOPE OF WORK:
Engineering Design, Procurement and Construction:
- Piping & Structures
CLIENT: Arab Tank Terminal Limited
LOCATION: Yanbu, Saudi Arabia
OWNER: Arab Tank Terminal Limited
DURATION: 2018 - 2021